White House Chronicle

News Analysis With a Sense of Humor

  • Home
  • King’s Commentaries
  • Random Features
  • Photos
  • Public Speaker
  • WHC Episodes
  • About WHC
  • Carrying Stations
  • ME/CFS Alert
  • Contact Us

A Tale of Two Dams: Catastrophe in the Making

August 18, 2014 by White House Chronicle 1 Comment

This is a tale of two hydroelectric dams. Two dams far from each other, but either of which could produce the next great humanitarian crisis.

The first is the Mosul Dam, which stretches across the Tigris River in a valley north of Mosul, Iraq. As dams go, this one is a civil engineering horror. It has been captured by the Islamic State, also known as the Islamic State of Iraq and the Levant.

Should the two-mile-wide dam fail, which is likely, Mosul will be wiped out and the damage will extend to Baghdad. Loss of life could reach 500,000, and millions could be deprived of water and power. An immense catastrophe piled on the daily pain of Iraq.
The second dam, far away in Southern Africa on the Zambezi River, is the Kariba. This 55-year-old dam, by some measures, is the world’s second-largest. It was a civil engineering masterpiece and has held up well, given the spotty maintenance by its owners — Zambia, on the north bank and Zimbabwe, on the south bank.

If the Kariba Dam fails, as it is predicted to do in three years without repairs, surging water would rip a vast trench down the length of the Zambezi River on its route to the Indian Ocean. The wall of water would take out another giant dam, Cahora Bassa, in Mozambique. Loss of life could reach 3.5 million, with untold damage to wildlife. Central Southern Africa would lose 40 percent of its electric supply.

While the Mosul and Kariba dams are linked in their potential lethality, they are very different structures.

The Mosul Dam was a rush job, ordered by Saddam Hussein in the 1980s without regard to the engineering realities on the site. It is anchored in gypsum, which dissolves in water. So leaks in the foundation have to be plugged daily with “grout,” a mixture of cement and sand. The U.S. Army Corps of Engineers said the Mosul Dam is fundamentally the wrong structure for the location, and called it the “most dangerous dam in the world.”

Even with careful tending, the Mosul Dam is in danger. According to a report in The Wall Street Journal, many of the workers who have kept the dam going fled when the Islamic State arrived, and only one dedicated manager is known to have remained.

The United States spent $33 million trying to stabilize the Mosul Dam, but the money, according to an inspector general’s report, was largely wasted. Now the United States cannot bomb near the dam for fear of destabilizing it further.

Apart from general-maintenance issues, the Kariba Dam issues are a little simpler. When the dam was built between 1955 and 1959, it was planned that the river flow would be controlled though six sluice gates set in the wall. These empty into a plunge pool before the water flows downstream.

The trouble is that the plunge pool has grown from an indentation in the riverbed to a vast crater 285-feet-deep. There it swirls around with great force and is eroding the basalt rock on which the dam is anchored. The dam is eating itself alive. All the sluice gates dare not be opened at once, and have not been since 1966.

The fix is a mixture of blasting the plunge pool, so the water goes downstream without creating a whirlpool, and injecting grout — in the form of underwater concrete — to shore up the foundation.

A consortium of the World Bank, the European Union and the African Development Bank this month agreed to provide $250 million to save Kariba. Engineers say the work must be done in the next three years or it will be too late.

If Zimbabwe and Zambia can agree on the contracts and let them in time, work should begin next year. But in that part of the world, the only thing that moves fast is the Zambezi River. The future of Mosul Dam is anyone’s guess. — For the Hearst-New York Times Syndicate

Email, RSS Follow
Email

Filed Under: King's Commentaries Tagged With: Cahora Bassa Dam, hydroelectric dams, Iraq, Islamic State, Islamic State of Iraq and the Levant, Kariba dam, Mosul Dam, Mozambique, southern Africa, Tigris River, Zambezi River, Zambia, Zimbabwe

Comments

  1. Adrian Piers says

    September 8, 2014 at 6:09 am

    Mr King, I must correct you on some facts.
    1. Kariba dam was planned with FOUR spillway gates, not six.
    2. Due to unprecedented floods during construction, the number was then increased to SIX.
    3. The original plan was to have the North bank turbines operational soon thereafter, thus letting the bulk of the water through that outlet.
    4. Due to political interference, a whole new hydro scheme was constructed on another river, the Kafue.
    5. Kariba therefore had an additional 20 years of unplanned spillage through the six gates, never considered in the design.
    Currently there are proposals to refurbish the wall and gates that are estimated to cost US$ 350 million. I have offered the authorites an alternative plan that will remove the spillway function from the dam wall completely and solve the problem forever. I estimate the cost to be less than one third of the above amount.
    The response has been disappointing. I can only conclude that there are vested interests that stand to personally gain financially from borrowing the money and the award of contracts, and are quite prepared to commission a white elephant.
    I challenge the World Bank and the African Development Bank to compare these alternative solutions before they proceed with what looks to me like waste of money that taxpayers will have to repay, and does not even solve the problem.
     

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

White House Chronicle on Social

  • Facebook
  • Twitter
  • Vimeo
  • YouTube
Europe Knows Russia and Is Deeply Afraid

Europe Knows Russia and Is Deeply Afraid

Llewellyn King

Europe is naked and afraid. That was the message at a recent meeting of the U.K. Section of the Association of European Journalists (AEJ), at which I was an invited speaker. It preceded a stark warning just over a week later from NATO Secretary General Mark Rutte, also speaking in London, who said the danger […]

A Commencement Address — Get Used to Rejections, We All Get Them Sometimes

A Commencement Address — Get Used to Rejections, We All Get Them Sometimes

Llewellyn King

It is school commencement season. So I am taking the liberty of sharing my column of May 10, 2024, which was first published by InsideSources, and later published by newspapers across the country.  As so many commencement addresses haven’t been delivered yet this year, I thought I would share what I would have said to […]

Can Our Waterways Provide a New Source of Baseload Power?

Can Our Waterways Provide a New Source of Baseload Power?

Llewellyn King

This article first appeared on Forbes.com Virginia is the first state to formally press for the creation of a virtual power plant. Glenn Youngkin, the state’s Republican governor, signed the Community Energy Act on May 2, which mandates Dominion Energy to launch a 450-megawatt virtual power plant (VPP) pilot program. Virginia isn’t alone in this […]

The Problem of Old Leaders — Churchill’s Sad Last Years in Office

The Problem of Old Leaders — Churchill’s Sad Last Years in Office

Llewellyn King

Old age is a thorny issue. I can attest to that. As someone told my wife about me, “He’s got age on him.” Indubitably. The problem, as now in the venomously debated case of former president Joe Biden, is how to measure mental deterioration. When do you take away an individual’s right to serve? When […]

Copyright © 2025 · White House Chronicle Theme on Genesis Framework · WordPress · Log in